Phase 1
Village Streets, Steetscape, Parking, Pedestrian Ways, Water & Sewer
Phase 1 of the Belmont Village Revitalization builds on existing accomplishments within the Village area and includes:-
Upgrades to the existing municipal water and sewer lines
-
Reconfiguration of Mill and Center Streets
-
Expanded and enhanced parking
-
Extension of sidewalks and other pedestrian enhancements
-
Steetscape improvements include sidewalks with connectivity to all points and beyond, street lighting and plantings and trees throughout the area.
Public Meetings
Third Public Meeting - April 11, 2012
A Third Public Meeting hosted by the Village Revitalization Committee to consider the final plans for Phase 1 of the Village Revitalization was held on Wednesday, April 11, 2012. Second Public Meeting - February 22, 2012
The Second Public Meeting hosted by the Village Revitalization Committee was held on February 22, 2012 at the Corner Meeting House.Revised Preliminary Design
First Public Meeting - December 15, 2011
The First Public Meeting was hosted by the Village Revitalization Committee on December 15, 2011. Much information was shared on preliminary options presented by the Project Design Team on Phase 1 of this multi-year project. Residents and Business Owners provided valuable comments regarding needed Village facilities and ammenities they would like to see incorporated into the plans.
Village District Revitalization Proposals Unveiled in Belmont Winnisquam Echo
Revitalization Committee Meetings
March 21, 2012
On March 21, 2012, the Revitalization Committee met
with representatives of Hoyle, Tanner Associates, Inc. to discuss Design Standards for the Phase 1 project. Click the pictures for more information. 

Preferred Option Map